Availability as per Installed Ca

INSTALLED CAPACITY of PSPCL for FY 2017-18 as on 30.09.2017

Name of Project

No. of Units

MW

Gross Installed Capacity (MW)

GNDTP, Bathinda

2

110

220.00

2

120

240.00

Total

460.00

GGSSTP, Ropar

6

210

1260.00

GHTP, Lehra Mohabbat (Unit # 1 & 2) (Stage-I)

2

210

420.00

GHTP, Lehra Mohabbat (Unit # 3 & 4) (Stage-II)

2

250

500.00

 

Total

920.00

TOTAL THERMAL

 

 

2640.00

Shanan

4

15

60.00

1

50

50.00

Total

110.00

UBDC-I

3

15

45.00

UBDC-II

3

15.45

46.35

 

Total

91.35

**RSPP

4

150

600.00

Less 20% J&K and 4.6% HP share from RSD

-147.60

Net RSD share of Punjab

452.40

ASHP

4

33.5

134.00

MHP-1&2

6

15

90.00

MHP-3&4

6

19.5

117.00

MHP-5

1

9

9.00

 

Total

216.00

Mini/Micro Hydel

 

 

 

5.60

TOTAL HYDRO

 

 

1009.35

TOTAL(HYDRO+THERMAL)

3649.35

PEDA & NRSE Private Projects within Punjab (excluding PSPCL's Own NRSE Projects i.e. UBDC & Mini/Micro Hydel Projects)

1261.92

Rajpura TPP

2

700

1400.00

Talwandi Sabo TPP

3

660

1980.00

GVK TPP

2

270

540.00

Total Installed Capacity within the State

8831.27

 

NRSE Private Projects outside Punjab

65.00

Central Sector (FIRM Share only)

4034.42

Share from BBMB

1161.28

Total Gross Installed Capacity (from all sources)

14091.97